​​​​​​Techniques for installatio and debugging of cnc spring coiling machine 
  1. Connect power of machine and decoiler.
  2. Load the wire on the decoiler .
  3. Install the wire feeding roller and front ,middle , rear wire guide ,coiling finger If no need to make torsion springs only need to install these tools . If have to make torsion springs as well, have to install torsion spring related cutter tools .
  4. More than 0.7mm wire diameter , have to install one pair /2 pieces rollers & front wire guide ,rear wire guide and less than 0.7mm wire diameter , have to install 4pcs rollers & front wire guide ,middle wire guide and rear wire guide .
  5. this tool can be used to adjust outside diameter .
  6. If marks occurred on the surface of springs , that means you didnt do chamfering on the surface of tools properly .You have to do chamfering.